The process of backup creation consists of several steps

  1. Protect
    During backup creation, all the required reference backups will be protected against removal, e.g. during the creation of a level 1 backup, the corresponding level 0 backup cannot be removed.
  2. Write
    The actual creation of a new backup.
  3. Validate
    Once the backup is fully written, it will be validated.
  4. Unprotect
    After that, the protection of the current backup and of all the corresponding reference backups will be released.
  5. Clean-up
    Expired backups will be removed, even the newly created backup if the expire time applies.
    Please note, that this operation can take a considerable time, especially if there is a large number of expired backups in the system. Unfortunately, there is no way to predict the duration.

After the successful cleanup, the backup cycle will be reported as finished.
Please note that during the whole backup procedure (including the clean up step), the database cannot be shut down. If another backup is scheduled and due while the backup run is in progress, it will be queued and executed directly thereafter.

Status information

EXAoperation

Progress is reported appropriate EXAoperation log services.

Timestamp Priority Service Message
2014-06-16 09:30:01.650358 NOTICE exa_db1 Backup started.
2014-06-16 09:31:10.218319 NOTICE exa_db1 Remove of expired backups started.
2014-06-16 09:54:59.587537 NOTICE exa_db1 Remove of expired backups finished.
2014-06-16 09:55:00.204568 NOTICE exa_db1 Backup finished.
EXASolution

The system table SYS.EXA_SYSTEM_EVENTS records the start and stop events but it does not present the single backup steps.

MEASURE_TIME EVENT_TYPE DBMS_VERSION NODES
2014-06-16 22:30:01.650358 BACKUP_START 4.2.10 4
2014-06-16 22:55:00.204568 BACKUP_END 4.2.10 4